NEW COGENERATION PLANT (GT-6) UNIT 7000– MOTOR OIL HELLAS CORINTH REFINERIES S.A.
TEKAM GENIKI ENERGY S.A. undertaken to execute on behalf of MOTOR OIL HELLAS the construction of a new 80MW combined cycle turbine at the Corinth refinery, in Ag. Theodoroi.
The tasks to be carried out are the following:
- Installation & connection of HV (150kV) and MV cable including related civil works.
- Erection of new 20kV substation including 150kV step down transformers, switchgears, bus ducts etc.
- Fire Detection & Fire Suppression (Inergen) systems for new substation.
- Installation of field instruments and cables
- Installation of turbine’s electrical & automation systems
- Earthing & Lightning protection
- Lighting
- Pre-commissioning & Commissioning
- QA/QC Management
- HSE Management